Infrastructure Projects Under Implementation co-financed by ISPA Programme

PLOVDIV - SVILENGRAD RAILWAY ELECTRIFICATION AND UPGRADING OF CORRIDORS IV AND IX

(summarized information for the period JUNE 2011 - DECEMBER 2011)

The impossibility for extension the funding deadline under ISPA/CF after the end of 2010 in relation to the continuous delays of already assigned construction contracts of Phase 1, Phase 2 and Systems lead to scope reduction of the preliminarily laid project under ISPA programme.

Splitting the project scope between ISPA and OPT

Scope under ISPA:

MTITC and the telecommunications business started elaboration of the national position on reforms in electronic communications in the EU

Experts from the Ministry of Transport, Information Technology and Communications, the Communications Regulation Commission and representatives of the telecommunications business started elaboration of the national position on the proposals of the